Koorana is opening a new preschool in Bass Hill in 2025 which is proudly funded by the NSW Government in association with Koorana Child and Family Services Ltd and private donors. Follow along with our build progress here.
Koorana Bass Hill Preschool
Purchased site
Completed
Purchased site
July 2021
Koorana Bass Hill Preschool
Council Approval
Completed
Council Approval
November 2023
Koorana Bass Hill Preschool
Building Tender Closed
Completed
Building Tender Closed
February 2024
Koorana Bass Hill Preschool
Breaking Ground / Demolition
In progress
Breaking Ground / Demolition
August 2024
Koorana Bass Hill Preschool
Lock up
Lock up
November 2024
Koorana Bass Hill Preschool
Interior Fit Out
Interior Fit Out
January 2025
Koorana Bass Hill Preschool
External Landscaping
External Landscaping
March 2025
Koorana Bass Hill Preschool
Launch
Launch
May 2025
Koorana Bass Hill Preschool
Purchased site
July 2021
Koorana Bass Hill Preschool
Council Approval
November 2023
Koorana Bass Hill Preschool
Building Tender Closed
February 2024
Koorana Bass Hill Preschool
Breaking Ground / Demolition
In progress...
August 2024
Koorana Bass Hill Preschool
Lock up
November 2024
Koorana Bass Hill Preschool
Interior Fit Out
January 2025
Koorana Bass Hill Preschool
External Landscaping
March 2025
Koorana Bass Hill Preschool
Launch
May 2025
Together we can build bright futures.
Our new Bass Hill Preschool will fulfill the urgent need for more early learning places in southwestern Sydney, with significant places reserved for children in most need.
Engaging creative play in our new Sand Kitchen, Ship and Tee-Pee
Active play spaces such as balance
beam, boulders, log steppers and outdoor deck
Purpose built accessible sandpit, space for quiet play and a beautiful sensory garden.
Our Build Progress
Previous
Next
Donations Received For Our Build.
Currently $45K of $840K
0%